Showing posts with label centerville. Show all posts
Showing posts with label centerville. Show all posts

Thursday, November 25, 2010

Albert Road Reconstruction Stirs Ozone Park Residents by Patricia Adams - Forum News

Read original...


City Begins Land Acquisition Process


Ozone Park property owners turned out in full force on Tuesday evening for what was originally billed as an emergency meeting of the Ozone Park Civic Association. The meeting was called after a “boiler plate” letter was sent to more than 500 residents who live on streets within the confines of HW411B, the street and sewer reconstruction of the Albert Road area.

Inclusion of the term eminent domain the letter sent a wave of panic through many residents who feared they may lose their property. Thankfully, despite the initial stress caused by the letter, there are no cases where a home or any other significant land parcels are in danger of being lost.

Department of Design and Construction fell under criticism because it failed to send details advising individual homeowners about how their property would be affected, if at all. “They [the city] could have spared the community this hysteria had they done their due diligence,” explained Councilman Eric Ulrich (R-Ozone Park).

But despite his criticism of the agency’s dissemination of information to the public, Ulrich says he is confident that the project will now move ahead. “I believe that construction will start as early as 2012. The acquisition process has begun and the project is fully funded. It will move forward.”

Ozone Civic President, Howard Kamph said at the end of the meeting he was happy with his decision at the last minute to allow the crowd to interact directly with the agency personnel. Kamph expressed concern over some additional provisions of the project which he said would include bike lanes and the return of Cohancy Street to a two-way. “If this project ever gets done, it will be a miracle,” Kamph said. “I’ve been hearing about it since I got here in 1981 and I have the DOT letters to prove it.”

Complete lists detailing the project were made available to all residents in attendance on Tuesday evening. Representatives from DDC reviewed individual properties with residents and advised them of any changes intended at their location. All homeowners were especially relieved to be informed that no residences were in jeopardy and that only a handful of structures, namely garages or sheds, are involved. The major alterations will be comprised mainly of residents losing some footage at curbside and other instances such as small retaining walls installed by homeowners. In all instances where the city would be acquiring property not already owned by them, financial compensation will be offered.

The original estimate to begin construction is early in 2013 and is expected to continue for approximately one year.

Sunday, November 21, 2010

Residents Seek Answers on Ozone Park Sewer Plan by Bryan Yurcan - Queens Chronicle

Read original...


Residents pack the Ozone Park Civic Association meeting Tuesday to speak with officials from the city Department of Design and Construction on the HWQ411B sewer project. PHOTO BY BRYAN YURCAN

Hundreds of residents came out to the Ozone Park Civic Association meeting Tuesday looking for answers about potential eminent domain proceedings in the Centreville area.
About 500 Centreville residents received letters last week from the city Department of Design and Construction regarding the long-proposed HWQ411B sewer project. The letters stated that the city might need to use eminent domain to acquire some property in order to complete the work.

Civic Association President Howie Kamph said he was flooded with calls from concerned homeowners, and decided to invite DDC officials to the meeting to speak to them directly.
Rather than conduct the meeting in a traditional manner, DDC representatives set up seven different stations, and — according to their address — residents went to the proper table to find out what, if any, property the city might need to take.


“This was the best way to do it, this way the DDC can have a one-on-one conversation with every homeowner,” Kamph said. “It’s better than an open meeting with everyone screaming.”


Originally proposed 30 years ago, the HWQ411B plan calls for the replacement of several water mains and sanitary sewers in the area, along with the additions of new storm drains, which would help alleviate the community’s long-time flooding problem.


According to Narayana Venugopalan, an assistant commissioner with the DDC, about 150 properties in the neighborhood will be affected.


He said homeowners will lose no more than five to 10 feet of property, mostly curbs and sidewalks in front of their residences.


“It won’t be more than a sliver,” he said.


A public hearing on the $40 million project is scheduled for Nov. 30. Venugopalan said work on HWQ411B will begin either in late 2011 or the spring of 2012.


“We are finishing this project,” he said of the long-delayed plan.


Ozone Park resident Anna Quarto was one of many who received the eminent domain letter and came to the meeting with concerns.


Quarto said she found the session to be informative and was glad to discover that no one will be losing their house.


“I think people in general got scared when they read that their property might have to be acquired,” she said.


Her husband, Lenny, said he is glad the project appears to finally be moving forward.
“It will definitely make Ozone Park better,” he said.

Thursday, March 20, 2008

More Excuses and Delays Anger Centerville Locals by Lee Landor - Queens Chronicle

Read original...

Rockaway resident Lew Simon scolds the city for continuing to delay a fully-funded and long-awaited reconstruction project promised to Centerville 25 years ago. (Lee Landor)

It was another meeting filled with empty promises and transparent excuses for residents of the Centerville section of Ozone Park.

On Tuesday night, they heard, once again, that HWQ411B — a 25-year-old, fully-funded, $40 million city project to reconstruct the broken roads of Centerville — has been delayed.

This time, representatives from the Departments of Transportation and Design and Construction blamed new policy changes for the holdup, which would push back the project’s start date by one year to the spring of 2011, or fiscal year 2012.

“Every year you say ‘next year’,” resident Lew Simon told DDC Program Administration Assistant Commissioner N. Venugopalan during the meeting, which was held in the Ozone Howard Little League center.

Venugopalan, speaking over frustrated sighs and sarcastic remarks, said the cause of the delay is the lengthy process of property acquisition. The city cannot begin construction — or complete design, for that matter — until it owns the titles to each of Centerville’s 28 blocks.

The DOT Queens borough commissioner, Maura McCarthy, told residents the city’s Law Department changed its property acquisition policy in 2006, forcing the agencies to redo any acquisitions they had already completed.

Using charts and a projection screen, Venugopalan estimated that by April 2010 the city will have completed property acquisition, the production of maps, designs and rendering and appraising land value.

Only after each homeowner — who will lose between 100 and 1,000 square feet of land through eminent domain — is compensated, can construction begin, he said.

The residents were skeptical. “I just hope we live long enough to see the project begin,” said Howie Kamph, president of the Ozone Park Civic Association.

Since 1983, the DOT, DDC and Department of Environmental Protection have been discussing the massive project to replace streets, sidewalks, curbs and pedestrian ramps, and install new water mains and sanitary and storm sewer systems in Ozone Park.

Having patiently waited for two-and-a-half decades for this seemingly never-ending process, the residents have requested that the city make temporary repairs. Walking around the neighborhood has become a frightening activity, according to Simon. “You can’t push baby carriages, wheelchairs. You can’t even walk without breaking a leg.”

But, in anticipation of HWQ411B, the city has refused to rebuild crumbling sidewalks — which cause frequent flooding — or to repave streets dotted with large potholes. According to McCarthy, once the DOT repaves a road, it cannot touch the road for at least five years.

Mitch Udowitch, a representative for state Sen. Serphin Maltese (R-Glendale), suggested that temporary repairs begin now and HWQ411B be rescheduled to begin in FY2013. This would leave five years between repaving and reconstruction.

But McCarthy warned that delaying the project would result in a loss of funding. Refusing to believe that, Udowitch reminded her that the project has long been fully funded.

Once they complete their land acquisition maps, the DDC plans to hold a meeting with homeowners at which it will explain how much land will be taken and what sort of construction will be done.

In April 2009, Venugopalan said the DDC and DOT will hold a public hearing and make its final design presentation. Currently, DDC plans include the reconstruction, repaving, rebuilding and installation of 10.5 miles of roadway, 150,000 square feet of sidewalks, 7.5 miles of curbs, 3 miles of water mains and 2 miles of sewer replacements.